Issuance of Building Permit / Electrical Permit / Mechanical Permit

SCHEDULE OF AVAILABILITY OF SERVICE:
Monday - Friday
8:00 am - 5:00 without noon break

WHO MAY AVAIL THE SERVICE: Owners of newly-constructed and proposed buildings/structures

HOW TO AVAIL THE SERVICE:
Requirements:Duration: 4 hours 37 minutes
colspan="4">
- 5 Copies of Zoning Certification from MPDC
- 5 sets of Sketch Plan and Specification duly signed by Civil Engineer/Architect
- 5 sets Detailed Estimates
- Photocopy of Land Title/Deed of Sale/Tax Receipt
- 5 sets Location Plan

Fee:
Based on the floor area

PROCEDURESRESPONSE TIME(Under Normal Circumstances)PERSON RESPONSIBLE
Application

Client shall approach the assigned staff at the Engineering Office together with the requirements
4 minutesENGINEERING STAFF
Evaluation/Examination of Documents

Engineering Staff examines the documents submitted
5 minutesENGINEERING STAFF
Ocular Inspection

Engineering Staff conducts site inspection
4 hoursENGINEERING STAFF
Assessment and Processing of Document

Engineering Staff assess and process the document
10-15 minutesENGINEERING STAFF
Payment of Fee

Client goes to the Treasurerīs Office and approach assigned staff for payment of fee
10 minutesMARILYN S. VALDEZ Administrative Assistant I
Approval and Releasing of Document

Municipal Engineer approves and Engineering Staff releases the document
3 minutesMARCIAL E. IDAGO Municipal Engineer